St. Petersburg Directorate of Transport Construction
GENERAL DESIGNER
‘Petersburg Dorservis’ Ltd.
GENERAL CONTRACTOR
‘Vozrozhdenie’ Ltd., ‘Mostootryad-19’ JSC
DESIGN STAGE
Detailed documentation – 2012
CONSTRUCTION STAGE
2013 — 2017
SCOPE OF WORK
design of superstructures (detailed documentation)
SIMILAR OBJECTS
TRAFFIC INTERCHANGES, POKLONNAYA GORA
OVERPASS NEAR POKLONNOGORSKAYA STREET ACROSS THE RAILWAY TRACKS OF THE VYBORG DIRECTION WITH APPROACHES
OVERPASS NEAR POKLONNOGORSKAYA STREET ACROSS THE RAILWAY TRACKS OF THE VYBORG DIRECTION WITH APPROACHES
- bridge schema —33.0+8х42+33+24 m
- total length —426.8 m
- carriageway clearance —2(Г-10)+2х1.5 m
- the entire weight of steel (superstructures) —1,978.4 t
- deck reinforced concrete slab —1,461+1,489=2,950 m³