DESIGN AND CONSTRUCTION STAGE
2015
TECHNICAL FEATURES
Composite bridge crossing under motorway and RR
Deck structure:
- Bridge length 1,334 m;
- Bridge schema: 6 х (2 х 110 m).
Deck structure:
- carriageway – continuous steel deck with orthotropic box slab. Dimensions Г 10+2х1.0) — RR — continuous steel truss 2х110 m under one way RR.
- Massive piers on piled foundation.
- Technical supervision is being conducted by Institute Giprostroymost Saint-Petersburg, Ltd.
SCOPE OF WORK
- Design of bridge structures;
- Construction Technology design;
- SAS&D design;
- Design of Construction MS.