CLIENT
Sevzapupravtodor
GENERAL CONTRACTOR
JSC VAD
DESIGN STAGE
Design documentation: 2011 – 2012
Working documentation: 2014
Working documentation: 2014
CONSTRUCTION STAGE
2014 — 2015
TECHNICAL FEATURES
- bridge diagram (for each direction) — 1 x 73.0 m;
- bridge length —28 m;
- bridge roadway overall dimension — 2(Г-9)+2х5 m;
- total weight of steel (superstructures) — 850 tonnes;
- reinforced concrete slab of superstructures — 260.2+252.3=512.5 m³;
- total volume of reinforced concrete — 593.8 m³.
SCOPE OF WORK
- development of architectural solutions;
- designing of main structures (design documentation and working documentation);
- designing of technology of construction;
- designing of SAC&D (design documentation and working documentation).
RECONSTRUCTION OF BRIDGE OVER THE VUOKSA RIVER
Reconstruction of the bridge over the Vuoksa River regarding the project.
The motor road from Saint-Petersburg through Priozersk, Sortavala to Petrozavodsk, including the constructed section from Saint Petersburg Ring Road through Skotnoe to Magistralnaya motor road at the section km 57+550- km 81+000, Leningrad Region.
The motor road from Saint-Petersburg through Priozersk, Sortavala to Petrozavodsk, including the constructed section from Saint Petersburg Ring Road through Skotnoe to Magistralnaya motor road at the section km 57+550- km 81+000, Leningrad Region.