DESIGN STAGE
2013 – 2014
CONSTRUCTION STAGE
2014 – 2017
TECHNICAL FEATURES
Viaduct of the Highway
  • our structure is designed  within straight in plane area with a length of 191.8m and on curved area of 1,200m along the roadway axis with transitional curves of 100m per each one
  • total curved area is 379.63m, the entire straight area is 917.8m
  • roadway clearance: 0.75+11.5+11.5+0.75m
  • spans and piers were designed per two-way traffic

Flyover #1
  • schema of structure 45х33m, the entire length – 1,494.36m

Flyover #2
  • schema 8х33+8х32.6+25х33+18+2х33+15+33m. Total length  –  1,490.86m
  • girders per 32.6m designed per adjacent piers of two flyovers
  • girders were completed of composite RC
  • deck structure height 1.95m (length 33 and 32.6m)
  • piles quantity – 4 pcs. 

Bridge over the Artemovka River
  • Bridge schema: 4х(3х42)m
  • Total length of the bridge span – 513.5m
SCOPE OF WORK
  • development of working documentation;
  • development of design documentation.
SIMILAR OBJECTS
SECTION OF RING-ROAD KAD AROUND SAINT-PETERSBURG FROM PRIOZERSKOE SHOSSE UP TO MOTORWAY ‘RUSSIA’, LOT 5
BRIDGE OVER THE ARTEMOVKA RIVER WITH VIADUCT ON FEDERAL HIGHWAY VLADIVOSTOK – NAKHODKA – PORT VOSTOCHNY, PRIMORSKIY KRAY
Overpass on PK33+85 on the Vladivostok – Nakhodka – Vostochny Port highway on the section km 18+500 – km 40+800 in Primorsky Krai.
Logo
Dynamic Heading