CLIENT 
  Mostostroitelny Trest 6 
  GENERAL CONTRACTOR 
  Mostostroitelny Trest 6, Mostootryad 37
 
  DESIGN STAGE 
  1995 — 1997
 
  CONSTRUCTION STAGE 
  1997 
  TECHNICAL FEATURES 
 - bridge diagram: (54+99+54) m
 - bridge total length: 217.9 m
 - limiting dimension: Г – (2000+3750+750+3750+2000) = 2 sidewalks per 0.75 m
 - carriageway total width - 23.5 m
 - bridge total width – 26.9 m
 - cross section: two steel box girders of 3 176 mm in height, the distance along the axes of the webs is 1 920 mm, the distance between the axes of the box girders is 12 220 mm, combined with an orthotropic carriageway slab on the top
 - total weight of superstructure steel - 2 040 tonnes
 
 SCOPE OF WORK 
 - development of SAC&D working documentation
 - development of Method Statement for installation of superstructure and construction of piers
 - field supervision
 
 SIMILAR OBJECTS 
  BRIDGE ACROSS THE MOSKVA RIVER NEAR THE VILLAGE OF SPAS 
  Reconstruction of the Moscow Ring Road. Road bridge across the Moscow River on the Moscow Ring Road.