CLIENT
Moscow Federal Enterprise ‘Road and Bridge Construction Department’
GENERAL CONTRACTOR
SC ‘Mosinzhproekt’
GENERAL DESIGNER
SC ‘Mosinzhproekt’
DESIGN STAGE
2020 – 2022
CONSTRUCTION STAGE
2020 – 2023
TECHNICAL FEATURES
- structures quantity – 6 flyovers
- total length of structures- 2.027 km
- length of retaining walls – 1.1 km
SCOPE OF WORK
Stage DD:
Stage WD:
- design of artificial structures
- MS design
- estimate documentation development
Stage WD:
- design of WD based on DD data approval via Federal Experts
- technical supervision
SIMILAR OBJECTS
SOUTH BELT ROAD
Construction of the road network with artificial structures and utility network rearrangement on the site of Kaspiyskaya Street up to 1-st Kotlyakovski lane (Construction Stage II).
Transportation interchange with Proletarsky Avenue, Kantemirovskaya Street and Moscow Ring Road under construction.
The site consists of six flyovers with approaches with retaining walls on piled foundation.
Transportation interchange with Proletarsky Avenue, Kantemirovskaya Street and Moscow Ring Road under construction.
The site consists of six flyovers with approaches with retaining walls on piled foundation.