CLIENT
JSC WHSD
CONTRACTOR
ICA Astaldi Ictas
OWNER
Northern Capital Highways, Ltd
DESIGN STAGE
2013 — 2014
CONSTRUCTION STAGE
2016
TECHNICAL FEATURES
  • Bridge schema: 60+110+240+110+60 m;
  • Total length – 580 m;
  • Carriageway clearance 2 х (Г – 17.5);
  • RC pylons;
  • Pylon heights – 124 m.
SCOPE OF WORK
  • Architectural conception design;
  • Main structures design;
  • Working Documentation per Cable Stayed Bridge;
  • SAC&D per the bridge structure;
  • MS development and issue;
  • Technical Supervision.
CABLE STAYED BRIDGE OVER THE PETROVSKY CHANNEL, SAINT PETERSBURG
The Bridge Crossing was conceived as a part of the important city Motorway Western High Speed Diameter. The structure is located on convex curve of 10,000 m. Projection of upstream clearance is 166х25 m and downstream clearance is 80х25 m. Foundations of piers were fulfilled as bored piles Ø1,500 mm. Deck cross-section is presented as a structure of four main girders of 1.76 m height within stay cable system. Abutments composed of six box type main girders of 1.76 m height. Bridge girders were connected via beams on distance of 65 m. (3 m per edge piers). Composite monolithic carriageway slab thickness is 220 mm. SSI2000 was an option of stay cable system with galvanized strands individually greased and coated with a high-density polyethylene sheath. The strands are used in accordance with the EN10138 standard. Total strands are seven wire 15.7mm diameter. Designated distance within stays is 13m.
SIMILAR OBJECTS
BOLSHOY OBUHOVSKIY CABLE-STAYED BRIDGE OVER THE NEVA RIVER, SAINT PETERSBURG
VIADUCT ALEXANDROVSKAYA FERMA, SAINT PETERSBURG