CLIENT
Department of Roads and Bridges Construction, Moscow
DESIGN STAGE
2019 — 2020
CONSTRUCTION STAGE
2020 — 2022
TRANSPORT JUNCTION INCLUDES
  • 2 side roads along  МKAD;
  • 10 exits;
  • 4 viaducts;
  • 1 pedestrian crossing.
TECHNICAL FEATURES
SIDE ROAD P1
  • one way , two way and three way road of – 1,021. 8 m, 
  • flyover – 119.5 m;
  • material - RC ; 
  • road schema 30.0+48.0+30.0 m; 
  • total width – 15.41 m;
  • carriageway width – 13.25 m.

SIDE ROAD P2
  • one way , two way and three way road of – 641,05 m, 
  • flyover – 119.4 m;
  • material - RC; 
  • road schema 30.0+48.0+30.0 m; 
  • total width – 15.41 m;
  • carriageway width – 13.25 m.

ARCHWAY PEDESTRIAN CROSSING
Located within Ostashkovskaya Street #30.
  • the arch has U-shape;
  • total length – 36.0 m; 
  • material - RC; 
  • total width – 3.0 m;
  • staircase width – 3.35 m; 
  • glazing – solid polycarbonate.
SCOPE OF WORK
  • Stage: DD, WD
  • General Design.
SIMILAR OBJECTS
VIADUCT OVER THE RR ON 19KM OF MMK – PAVLOVSKAYA SLOBODA - NAKHABINO MOTORWAY
TRANSPORTATION INTERCHANGE MKAD ON THE INTERSECTION OF OSTASHKOVSKOE SHOSSE
Transportation interchange is located within North-East area of Severo-Medvedkovo District of  Moscow about 90-91 km from MKAD.
Type of works: new construction and reconstruction.
The Project includes reconstruction of Ostashkovskoe Shosse Transportation Interchange and MKAD with exits and pedestrian crossings.
The following measures should be completed:
  • MKAD transportation flow separation together with  exits flows from adjacent roadways; 
  • Spots of left turn transportation flows intersections elimination within cloverleaf types transport junctions;
  • Arrangement of two extra left turn exits.
Logo
Dynamic Heading