CLIENT
Federal Enterprise ‘Russian Motorways’, ‘Avtodor Ltd’
GENERAL DESIGNER
SC ‘Institute Giprostroymost Saint-Petersburg’
DESIGN STAGE
2021
CONSTRUCTION STAGE
2024
TECHNICAL FEATURES
- road class — IB
- designated speed — 120 km/h
- road length per Stage 6 — 132 km
- road length per Stage 7 — 82 km
- road length per Stage 8 — 70 km
- lane width — 3.75 m
- lanes quantity — 4 (2 per each direction)
SCOPE OF WORK
Stages DD and WD:
- General Design;
- Design and survey works;
- DD and WD development;
- Technical Supervision.
SIMILAR OBJECTS
SPEEDY HIGHWAY М-12 ‘MOSCOW – NIZHNIY NOVGOROD – KAZAN’
This 800 km long highway should provide that essential link between the territories of the Moscow, Vladimir and Nizhny Novgorod regions as well as toward the republics of Chuvash plus Tatarstan. M-12 is considered as a main part of the International Transportation Corridor ‘Europe - Western China’.
Stage 6 - 454 –586 km
Our road should pass partly through the Nizhny Novgorod Region with a certain extent through the territory of the Chuvash Republic. We designed the bridge crossing over the Sura River with challenging length of 930.5 m.
Stage 7 - 586 –663 km
This Stage is included the passage through the territory of the Chuvash Republic and the Republic of Tatarstan, from the intersection with busy A-151 Federal Highway ‘Tsivilsk – Ulyanovsk’ to the junction with the R-241 Federal Highway ‘Kazan – Buinsk – Ulyanovsk’ passes through the territory of two municipal districts of the Chuvash Republic including three municipal districts of the Republic of Tatarstan with a bypass of nearest settlements.
Stage 7 including structures:
Stage 8- 663 – 729 km:
It should run from the intersection with the R-241 Federal Highway ‘Kazan – Buinsk – Ulyanovsk’ to the traffic circle of ‘Sorochye Gory – Shali local highway ‘. The most important event should be the construction of a new bridge crossing over the Volga River, which shall make it more comfortable for motorists regarding status of northern bypass of Kazan, as well as significant unload of existing ferry crossings.
Stage 8 including structures:
This Stage covers artificial structures counting bridges and overpasses. Part of this route with the entire 24 km coincides with a bypass of Kazan, which is being constructed.
Stage 6 - 454 –586 km
Our road should pass partly through the Nizhny Novgorod Region with a certain extent through the territory of the Chuvash Republic. We designed the bridge crossing over the Sura River with challenging length of 930.5 m.
Stage 7 - 586 –663 km
This Stage is included the passage through the territory of the Chuvash Republic and the Republic of Tatarstan, from the intersection with busy A-151 Federal Highway ‘Tsivilsk – Ulyanovsk’ to the junction with the R-241 Federal Highway ‘Kazan – Buinsk – Ulyanovsk’ passes through the territory of two municipal districts of the Chuvash Republic including three municipal districts of the Republic of Tatarstan with a bypass of nearest settlements.
Stage 7 including structures:
- bridges;
- flyovers;
- wildlife crossings;
- technological approaches – 35 pcs.;
- sound barriers – 13.023 km
Stage 8- 663 – 729 km:
It should run from the intersection with the R-241 Federal Highway ‘Kazan – Buinsk – Ulyanovsk’ to the traffic circle of ‘Sorochye Gory – Shali local highway ‘. The most important event should be the construction of a new bridge crossing over the Volga River, which shall make it more comfortable for motorists regarding status of northern bypass of Kazan, as well as significant unload of existing ferry crossings.
Stage 8 including structures:
This Stage covers artificial structures counting bridges and overpasses. Part of this route with the entire 24 km coincides with a bypass of Kazan, which is being constructed.