CLIENT
Road Administration of Kaliningrad
GENERAL CONTRACTOR
VAD Ltd
DESIGN STAGE
2015
CONSTRUCTION STAGE
2016
TECHNICAL FEATURES
- local road classification – IB
- junction length – 24.6m
- carriageway schema – 2 x (19 + T-0.75)m
- total weight of RC deck – 2,038t
- total RC volume – 2,445m3
- RC volume per deck – 815 m3
Transportation interchange PK212+47.94 Exit 2 toward Moskovskiy Prospect
- junction schema – 12.2 + 2.1 + 12.2
- total length – 53.32m
- carriageway dimension -15.75 +T- 0.75m; 13.25 + 3+ 9.5 +T-075m
- steel volume per deck – 359t
- whole weight of RC slab – 1,200t
- total RC volume – 1,777m3
- RC volume per deck – 480 m³
Transportation interchange PK214+68.62 through Moskovskiy Prospect
- local road classification — IB
- viaduct schema -2 x 18.0 + 12. 52 +2 x18m
- junction length – 91.38m
- carriageway schema -19 + T-0.75m; 13. 25 +3 +9.5 + T-0.75m
- steel volume per deck – 728t
- overall weight of RC slab – 2,488t
- total RC volume – 2,829m3
- RC volume per deck – 995 m³
SCOPE OF WORK
- WD design
- SAC&D design
SIMILAR OBJECTS
RING ROAD OVER KALININGRAD CITY
First Stage of the remarkable bypass of Kaliningrad City designed and completed by our Company over beautiful and popular resort of Zelenogradsk City with the approach to International Airport Khrabrovo (Fliegehorst Powunden).
Fulfilled part of the bypass is composed of the following:
The entire project was successfully accomplished back in 2009. ‘Ring Road of Kaliningrad City’ is the comfortable link from the International Airport to local resorts Svetlogorsk, Zelonogorsk plus such settlements as Pionerskoe, Baltiyskoe and Yantarniy.
Engineering structures of the I-st Stage of Construction:
Engineering structures of the IV Stage of Construction:
Transportation interchange PK2+12.59 Exit 2 toward Moskovskiy Prospekt:
Transportation interchange PK181+06 toward Gurievskaya Street
Aged grade-crossing with Gurievskaya Street was completed in the same level. Reconstruction project is being conceived via double levels without arrangement of exits i.e. to Gurievskaya Street and toward Ring Road.
Fulfilled part of the bypass is composed of the following:
- Length of the I-st Stage of Highway ‘Primorskoe Ring’ -26.7 km
- Lanes quantity – 4pcs
- Embankment width -28.5km
- Designated speed -120km/h
The entire project was successfully accomplished back in 2009. ‘Ring Road of Kaliningrad City’ is the comfortable link from the International Airport to local resorts Svetlogorsk, Zelonogorsk plus such settlements as Pionerskoe, Baltiyskoe and Yantarniy.
Engineering structures of the I-st Stage of Construction:
- Bridge over the channel PK 8+54
- Viaduct on the transportation interchange PK12+35.6
- Flyover on the junction PK10+80
- Viaduct on the Highway Orlovka-Gurievka PK24+74.85
- Bridge over the Gurievka River PK33+67.12
- Zelenogradka River Bridge PK37+0.5
- Cattle route PK78+80.7
- Viaduct on the transportation interchange PK91+39.04
- Flyover on the junction PK99+78.4
- Kurovka River Bridge PK119+73
- Bridge over the channel PK 114+34.6
- Viaduct on the transportation interchange PK174+06
Engineering structures of the IV Stage of Construction:
- Bridge over the Spokoinaya River PK6+0.7(approach to Resort Pionerskiy)
- Viaduct on railroad PK33+20.03(approach to Resort Pionerskiy)
- Bridge over the Zelenogradka River PK180+15.66
- Medveshya River Bridge PK206+50
- Viaduct on the motorway Kovrovo-Sokolniki PK242+38
- Overpass on the motorway Roshino-Dachi PK264+87.0
- Bridge over the Aleyka River PK269+59.40
- Viaduct on motorway Roshino-KulikovoPK290+27
- Bridge over the Zabava Creak PK308+05
- Freeway junction on Pionerskiy-Romanovo PK328+58
- Bridge over the Spokoinaya River PK336+82.75
- Viaduct on railroad PK349+35
- Flyover on the transportation interchange PK373+39.28
- Primorskiy Resort Bypass reconstruction, II Stage
- Reconstruction of Northern part of Kaliningrad Bypass and Moskovskiy Prospekt
- Junction
Transportation interchange PK2+12.59 Exit 2 toward Moskovskiy Prospekt:
- local road classification – II
- viaduct schema – 17.93 + 12.58 + 17.93
- length of viaduct – 49.34m
- carriageway schema – 11.5 + 2 x 0.75
- total steel per deck – 140t
- deck RC slab – 538t
- backfilled wall – 110.8m
- total RC volume – 1,846m3
- RC volume per deck – 215 m³
Transportation interchange PK181+06 toward Gurievskaya Street
Aged grade-crossing with Gurievskaya Street was completed in the same level. Reconstruction project is being conceived via double levels without arrangement of exits i.e. to Gurievskaya Street and toward Ring Road.