CLIENT
State-owned Company Russian Motorway Roads
GENERAL CONTRACTOR
AO KROKUS
GENERAL DESIGNER
AO Institute Giprostroymost Saint-Petersburg
DESIGN STAGE
2016 — 2018
CONSTRUCTION STAGE
2016 — 2021
TECHNICAL FEATURES
Construction Indices Lot No.1
Standard Temporary vertical loads:
- Russian Grade Road IА, length — 49,5 km
- Designated speed — 140 km/h
- Lanes quantity — 4 pcs.; 6 pcs (Stage II PK 2.417 + 09.56 — PK2.912 + 00)
- Lane width — 3,75m
- Carriageway width — 2×7,5 м ; 2х11,25 м (Stage II PK 2.417 + 09.56 — PK2.912 + 00)
- Emergency lane — 3,75m
- Deviding lane — 6,0m
- Junctions of different levels — 4 pcs; 5 pcs (Stage II PK 2.417 + 09.56 — PK2.912 + 00)
- Bridge crossings— 50 pcs; 53 pcs (Stage II PK 2.417 + 09.56 — PK2.912 + 00)
Standard Temporary vertical loads:
- per artificial structures А14, Н 14
- per road pavment 115 kN
SCOPE OF WORK
- Set of measures preparation reckoning state-of- art structures with utility lines optimization, regarding 1-st Stage of construction with volume required for technical decisions approval via the board of Government Technical Experts Committee.
- Approval of optimized solutions of ‘Avtodor’ Technical Experts together with presentation materials.
- Total set of works completion concerning work documentation preparation regarding construction site Central Ring Road of Moscow Region (toll road after the completion) including optimization options, approved by State-owned Company Avtodor.
SIMILAR OBJECTS
CENTRAL RING ROAD OF MOSCOW REGION
Construction of Central Ring Road of Moscow Region (toll road after the completion). Initial Stage of construction. Lot No.1