CLIENT
Federal Enterprise ‘Аvtodor’
CONTRACTOR
‘Volgogradstroy Ltd’
DESIGN STAGE
2020 – 2023
CONSTRUCTION STAGE
2021 – 2024
TECHNICAL FEATURES
- bridge schema: 6х84.0 m
- length of the bridge: 517.2 m
- clearance: 2(Г-10.5)
- lanes quantity: 4 pcs
SCOPE OF WORK
Stage DD:
Stage WD:
- bridge design development
- traffic management design
- utility lines rearrangement
- external illumination design, power supply, drainage, navigation lights arrangement, including transportation safety measures
- linear structures design
- construction arrangement design
- measures against karst factors
- environment protection measures
- fire safety measures
- structural monitoring per construction stage
- monitoring performance during service stage
- estimate development.
Stage WD:
- technical supervision
BRIDGE OVER THE SVIYAGA RIVER
Bridge crossing over the Sviyaga River is being conceived as a part of М-12 Highway ‘Moscow– Nizhny Novgorod – Kazan', Stage VII 586 –663 km in Chuvash Republic, Tatarstan. The above structure is being installed within intersection of А-151 Federal Highway ‘Civilsk – Ulyanovsk’ up to the subsequent Highway Р-241 ‘Kazan – Buinsk – Ulyanovsk’ Stage VII.III started from Bolshie Kaybitsy Settlement up to Federal Highway Р-241.
The bridge over the Sviyaga River within the Federal high-speed Highway M-12 "Moscow - Nizhny Novgorod – Kazan". It connects the Kaibitsky, Apastovsky and Verkhneuslonsky Districts of Tatarstan.
The bridge over the Sviyaga River within the Federal high-speed Highway M-12 "Moscow - Nizhny Novgorod – Kazan". It connects the Kaibitsky, Apastovsky and Verkhneuslonsky Districts of Tatarstan.
SIMILAR OBJECTS