CLIENT
Directorate for construction of very important objects of Khyakimlik of the city of Ashkhabad
GENERAL CONTRACTOR
SC ‘PO ‘Vozrozhdenie’
DESIGN STAGE
2009 — 2011
CONSTRUCTION STAGE
2009 — 2012
TECHNICAL FEATURES
- bridge diagram – (42+63+42) m
- bridge length – 156 m
- limiting dimension: 1,5 м + 3 х 3,5 m
Retaining walls
- total weight of reinforced concrete offoundations and retaining walls – 4747.5 tonnes
SCOPE OF WORK
- general design
- development of architectural solutions
- working project stage
- development of technology of construction
- development of SAS&D
- development of Method Statement
- development of Construction Method Statement
- fulfillment of calculations with development
- of specific technical specifications for designof seismic structures
- technical inspection
- participation in tests
- field supervision
- undergoing of expert examination of Turkmenistan
SIMILAR OBJECTS
BRIDGE OVER THE KARAKUM RIVER IN LINE OF NIYAZOV PROSPECT IN THE CITY OF ASHKHABAD, TURKMENISTAN
Two adjacent, separate for each direction of movement, beam-type steel-reinforced concrete span structures.