DESIGN STAGE
2020
SCOPE OF WORK
Stage WD:
- Calculation of FGT structural elements ;
- Engineering calculation adjustment;
- Reinforcement of RC structures;
- Explanatory notes preparation.
ARCTIC LNG-2
Arctic LNG 2 in considered the construction of three production lines for the manufacture of Liquefied Natural Gas (LNG) with a capacity of approximately 6.6 million tons annually and gas condensate up to 1.6 million tons per year. Our resource base regaring the facility is the "Morning Field", located on the Gydan Peninsula in the Yamal-Nenets Okrug, about 70 km from the “Yamal LNG”. Being produced LNG to be stored in refrigerated membrane-type tanks (with a total capacity of 229,000 m³ per platform), located on a Foundation of Gravity-Type (FGT).
FGT technology:
Production of FGT, assembling performance and modules installation is carried out within dry docks in the center of construction of large-capacity marine structures by Murmansk near the Belokamenka Village, and then FGT are towed to the site of the plant. Design of FGT is not being considered for loads in-service under extreme climatic conditions only, but also to withstand the required transportation loads.
FGT technology:
Production of FGT, assembling performance and modules installation is carried out within dry docks in the center of construction of large-capacity marine structures by Murmansk near the Belokamenka Village, and then FGT are towed to the site of the plant. Design of FGT is not being considered for loads in-service under extreme climatic conditions only, but also to withstand the required transportation loads.